Preparation for Installation of the Instrument Landing System

$2,608,854

Completion Date

08/20/2020

This design-build project provided preparatory work for the installation of a new Instrument Landing System (ILS). The ILS consists of an antenna system with primary components at two sites (i.e., Glideslope and Localizer) located at opposite ends of the runway. Work at the two sites consisted of removing and disposing of existing antenna equipment and equipment pads; site preparation for new equipment pads; installing underground conduits for power and communications cabling; installing grounding systems; constructing new equipment pads; and paving new access roads. 1,700 LF of underground fiber was installed to facilitate communications between the two sites. 500 LF of power ductbank and three transformers were installed to provide power for equipment at the two sites. Airfield markings, signage and installation of new survey monuments for ILS calibrations were also part of the scope this contract.

Repairs of BUMED Facilities, B993

$2,121,420

Completion Date

7/31/2019

Design-build repairs at Naval Air Station Whidbey Island Hospital including: Provision of a new sloped roof structural attic truss over the existing roof of the "Duct House" sheltering multiple electrical conduits. Replace existing roof at the Hospital’s Emergency Management, Linen Inventory, and Mail Room areas. Restore loading dock and construct a ramp providing a warehouse receiving area and emergency egress. Provide three supplemental cooling only units.

Replace Fire Alarm Systems B7000 & B7001 at NBK Bangor

$1,255,500

Completion Date

3/20/2018

Design-build fire alarm replacement of obsolete fire alarm systems in two industrial manufacturing facilities located in lower base (i.e., higher level security) at NBK Bangor. Designed and installed temporary fire alarm systems to enable disabling the existing systems in their entirety. Coordinated construction with various commands within each facility.

Restore Ventilation NHB B1, Phase II

$7,099,512

Completion Date

10/4/2017

Code-required modification and replacement of 7 air handling units (AHUs), 1 heating & ventilation (HV) unit, 19 fans, and 14 pumps on HVAC systems serving administrative areas, operating rooms, exam rooms, laboratories, and service areas. Extensive phasing, infection control, and outage coordination was required to maintain hospital operations.

Repair HVAC Periscope Shop

$1,682,058

Completion Date

6/19/2016

HVAC system upgrade to meet clean room standards. Scope included selective demolition of existing system; installation of new hot/chilled water generating equipment; air distribution ductwork; control systems; equipment support; electrical power and lighting; installation of a new splined panel ceiling and wall repairs; fire protection system revisions; and commissioning.

Repair Boiler Feedwater System

$2,671,763

Completion Date

7/5/2016

Phased replacement of three existing boiler feedwater pumps with 4-stage, horizontal, specialty pumps; provision of one spare pump; installation of 300 LF of new, seismically-restrained and insulated 8"Ø ductile iron pipe main and reconfigured header pipe main manifold; variable frequency drives and controls; and flow meters.

Energy Conservation, Phase 3

$3,417,288

Completion Date

11/22/2015

Design-build energy conservation project consisting of a combination of lighting and lighting control strategies; HVAC optimization via use of VFDs and controls; water conservation measures; point-of-use hot water heating; thermal envelope upgrades; weatherization improvements; and infra-red heating in 36 different buildings.

North Reservoir

$4,065,381

Completion Date

8/8/2014

Construction of a 4 million gallon above-grade, covered steel water reservoir. Scope included high performance coatings, telemetry, steel access stairs and platforms, and protective perimeter fencing. Associated improvements included a remote valve station, over one mile of of fill and main distrtibution piping, and road improvements utilizing pervious asphalt pavement.

Security Alarm Upgrade

$4,187,439

Completion Date

4/17/2015

Design-build upgrade replacement and integration of legacy Access Control Systems (ACS) and Intrusion Detection Systems (IDS) throughout Naval Base Kitsap, Bangor and Bremerton. Scope encompassed networking new ACS and IDS in over 100 different facilities serving over 150 different commands and using the Navy's secure network to connect signals to the Regional Dispatch Center.

P980 Armory

$1,310,071

Completion Date

1/30/2013

Design-build renovation and 2,000 SF cast-in-place concrete addition to convert portions of an existing vehicle garage facility into two separate armories complete with high-severity, bullet-resistant entry doors and weapons issue ports; Class 5A armory vault issue doors; specialized ventilation for weapons cleaning equipment; and administrative and staff offices.

B19 HIMMS Records & Dispatch

$1,555,251

Completion Date

5/9/2011

10,000 SF renovation of the B19 warehouse and conversion to a medical dispatch center and records storage facility complete with administrative offices, patient registration and waiting areas, mailroom, and emergency monitoring and dispatch offices. Complete interior demolition in support of new interior partitioning, finishes, and mechanical and electrical systems.

Bldg 13 Energy Upgrades

$596,966

Completion Date

5/24/2011

Replaced a legacy chiller unit with a new 200-ton, oil-free frictionless magnetic bearing air-cooled centrifugal water chiller. Coordinated replacement to support the ongoing operations of the research faclities served by the chiller. Scope included piping reconfiguration, integration into the existing DDC system and sequence of operations, and miscellaneous interior improvements to support the work.

B460 Repair Large Slab Rolling Doors

$1,038,360

Completion Date

09/08/2020

This project restored operation of four 60-foot tall large slab rolling doors at the west end of Building 460 in the Controlled Industrial Area (CIA) of the Puget Sound Naval Shipyard. Restoring operation to the doors involved retrofitting/restoring the gearboxes; replacing motors, control equipment, and electrical wiring; and providing new enclosures and appurtenances. Audible and visual signaling systems, limit switches and interlocks were installed to facilitate the safe operation of the doors. Deteriorating door panels were restored and painted inside and out. Broken glass panes were replaced. Replacement of aesthetic features adhered to historical restoration requirements.

Replace Boilers 1 & 2 at Steam Plant

$3,132,900

Completion Date

03/11/2020

Design-Build Replace Boilers 1 and 2 at the Steam Plant, B384 included the design of a new steam system, demolition and removal of two of three 45,000 pounds per hour (pph) (1300 boiler horse power (BHP)) water tube boilers in the central heating plant and installation of two new 20,700 pph (600 BHP) fire tube boilers. Steam service was maintained by the third existing boiler while replacement work was completed. Boiler replacement scope involved structural upgrade of the existing raised concrete floor slab, reconnection of all services, including feedwater, vent piping, fuel piping, and instrumentation.

Upgrade Tunnel D Electrical

$1,747,400

Completion Date

12/28/2017

Design-build electrical upgrade including installation of new explosion-proof (EP) primary power conduits; conductors; EP electrical panels; EP lighting fixtures and power conduits; and EP power receptacles. Design included photometric study to ensure illumination and uniformity criteria were satisfied. Provided temporary power service to maintain operation of critical fuel tank monitoring system during construction.

Retrofit Infrastructure Electrical Systems

$10,026,121

Completion Date

Under Construction

Provided new electrical infrastructure for the SORCC campus including 1,900 LF of new underground ductbank; renovation of historic B231 to house new switchgear; two new 1,500 kW diesel engine generators for emergency power; 750 kW load bank; 1.2 MWDC solar energy electrical power generation system; and automated switchgear with paralleling controls.

Replace 2300 Volt Substations

$2,381,375

Completion Date

6/15/2016

Provided upgraded electrical inftrastructure to replace three substations at the Puget Sound Naval Shipyard. Provided new transformers, underground electrical distribution, circuit breakers, feeder lines, commissioning of all new equipment items, and associated substation building improvements. Coordinated outages and cut-overs to and from temporary power to facilitate base operations.

Electrical Distribution NHB

$4,544,396

Completion Date

12/22/2015

Upgrade and replacement of critical electrical infrastructure and life safety system elements including new ATS for existing diesel engine emergency generators; UPS system upgrade for phone and information management systems; electrical load redistribution; critical branch circuit installation; Motor Control Center replacement; PA system upgrade; and FA, exit signage, and emergency pathway lighting upgrades.

VA B100 4E MICU/CCU

$5,122,378

Completion Date

6/8/2015

Construction of a 12,000 SF Medical Intensive Care/Critical Care Unit in a vacated hospital wing. Facility consisted of 14 patient rooms, 4 isolation rooms, nursing stations, staff conference/break room, administrative offices, and support spaces. Improvements included new mechanical, medical gas, and electrical systems; interior partitions and finishes; service headwalls and booms; and patient lift systems.

HCC Building 4 Noise Reduction

$2,200,178

Completion Date

8/27/2013

Renovation of the campus' circa 1967 Performing Arts Center including selective demolition and hazmat abatement in support of the installation of new interior partitions, finishes, mechanical and electrical systems, and exterior building envelope systems. The building included an auditorium, soundproof practice rooms, classrooms, and service spaces.

MLA Backlighting

$2,943,073

Completion Date

2/13/2013

Design-build replacement of an obsolete quartz halogen backlighting system with a new, energy-efficient LED system for the high-security Main Limited Area (MLA). Design work included engineering and photometrics. Provided new electrical infrastructure to support the four mile perimeter protection system. Phased construction to maintain perimeter protection throughout construction.

B2050 Medical/Dental Clinic Renovation

$6,857,079

Completion Date

4/25/2012

31,750 SF renovation and 3,500 SF addition to a fully operational Medical/Dental clinic. Scope included total HVAC system replacement, repartitioning, interior finishes, and electrical improvements. Concrete and steel addition provided space for administrative offices and medical exam rooms. Extensive phasing and provision of temporary facilities to accommodate ongoing clinic operations.

Heating Oil Tank Modernizations

$1,032,082

Completion Date

9/1/2011

Replacement of nine underground fuel storage tanks with 1000-gal to 5000-gal double-wall tanks. Also replaced four existing above ground tanks. Provided double-wall supply and return fuel line piping and leak detection systems. Site restoration involved asphalt road/parking lot patching; concrete curb, gutter and sidewalk; and hydroseed with temporary irrigation.

Renovate Dorms 564, 565, 567

$8,019,249

Completion Date

4/15/2013

Phased renovation of three 12,900 SF dormatory buildings with a total of 326 units. Interior work involved demo/abatement and included new fixtures, finishes, and upgraded M&E, fire alarm, and energy management systems. Exterior work included masonry restoration, balcony railings, concrete tile roof (at B567), and copper gutter/downspout repairs. Sitework included new transformers and electrical services.

Environmental Monitoring and Control Upgrade VA Puget Sound

$377,171

Completion Date

08/20/2020

Project scope involved upgrading the environmental monitoring systems at an operational animal research laboratory at the VA Puget Sound Health Care System’s Columbian Way Campus. Continuous coordination and communication with research staff ensured minimal disruption to laboratory operations. Advance Lighting Modules and temperature/humidity sensors were replaced in 28 different rooms located in three different buildings. System operation was maintained using the legacy control panel until all ALMs and sensors were installed. A new control panel replaced the legacy control panel and provided enhanced reliability and functionality.

Repair and Replace Stripper Tank System

$3,263,000

Completion Date

2/21/2019

Repair of the stripper tank system in Building #2547. Replace existing built in tanks, ventilation, fire protection, electrical system, and piping equipment with code compliant equipment and infrastructure. This includes hazardous materials abatement and disposal.

Aviation Battalion Headquarters BNHQ

$11,120,000

Completion Date

Under Construction

New construction of an 18,600 SF, 2-story concrete, masonry, and steel headquarters/training facility complete with interior finishes, elevator, radiant hydronic heating, and electrical/low voltage systems. Site development included installation of building power and communication services, extensive site drainage, and concrete and asphalt paving. Achieved LEED Silver certification.

Lighthouse Church Tenant Improvements

$870,000

Completion Date

9/12/2016

Provided pre-construction and construction services for a 7,300 SF tenant improvement to provide administrative offices and multi-use meeting space. Ministry center included a full kitchen complete with induction cooking and Type II hood; sound isolated music/recording room; and a multipurpose meeting room with acoustically-rated folding panel partition wall.

Replace HVAC System NHB

$7,181,526

Completion Date

10/3/2016

Code-required modification and replacement of 8 air handling units (AHUs), 15 fans, 8 variable air volume (VAV) boxes, and 16 pumps on HVAC systems serving patient care areas and the emergency department. Extensive phasing, infection control, and outage coordination was required to maintain hospital operations.

Sunny View Village

$4,137,066

Completion Date

5/18/2015

Construction of a new 25,000 SF, 26-unit multifamily affordable housing development consisting of four 2-story buildings of wood frame construction, mechanical and electrical systems, and interior and exterior finishes. Sitework including earthwork, utilities, concrete and asphalt paving, landscaping, and an on-site waste water treatment facility.

SERA Playground & Sprayground

$2,672,683

Completion Date

6/27/2014

Construction of a public parks facility for Metro Parks Tacoma. Scope included earthwork, domestic water, gravity sanitary sewer and power for construction of a 6,000 SF playground, 5,000 SF sprayground, restroom building, specialty concrete features, colored concrete paving, asphalt paving, irrigation, seeding, and planting.

Refurbish Track & Field

$1,394,125

Completion Date

10/9/2012

Design-build replacement of existing track and field facility using state-of-the-art, SPRINTURF Ultrablade MX™ synthetic turf over a meticulously prepared subgrade with an extensive subsurface drainage system. Worked with the Navy to resolve cost and time impacts associated with unsuitable soil materials encountered beneath a significant portion of the field.

Install Active Vehicle Barriers

$1,319,872

Completion Date

5/25/2012

Design-build installation of two active vehicle barrier systems at the Trident and Trigger base access gates. Designed and installed power, drainage, and control utilities in support of the vehicle barrier systems. Coordinated vehicular and pedestrian traffic control with construction activities to maintain constant access through these two primary base access points.

Replace Freight Elevator

$604,918

Completion Date

9/20/2012

Replaced the existing S-1 freight elevator with a new gearless traction freight elevator complete with modernized safety features and microprocessor controllers. Performed a structural study to assess the existing floor loading capacity in support of the decommissioning and removal of the legacy elevator's hoist and governor assembly, which weighed in excess of one ton.

Replace Steamlines

$384,227

Completion Date

10/11/2011

Phase II of a campus-wide conversion from centralized steam to building-specific, natural gas powered heat exchangers for hot water and heat generation. This phase involved decommissioning portions of the legacy high-pressure steam system and installating new, gas powered equipment for B6 and B61 and integration into the campus energy management control system.

Child Development Center

$12,289,295

Completion Date

10/27/2011

Design-build 27,000 SF child development facility providing administrative offices, auditorium, commercial kitchen, and 17 classrooms with capacity for 218 children. 6.5-acre site development included 78 parking stalls, covered walkways, and three play areas with state-of-the-art play equipment. LEED Gold certified design featured solar panels, a wind turbine, LED lighting, and accommodations for future geothermal.