$955,000
Repair AHUs - Building 03096, JBLM, WA
Completion Date
8.16.2021
Provided Administrative Building 03096 with a new HVAC heating system consisting of three air-to-air heat pumps and eight variable air volume (VAV) terminal units with electric heat. With a few exceptions, the new equipment and ductwork utilized existing equipment locations and ductwork routing. The new Direct Digital Controls (DDC) were integrated into JBLM’s base-wide DDC system. A phased approach was used to support continuous building use throughout the construction.
$2,608,854
Preparation for Installation of the Instrument Landing System
Completion Date
08/20/2020
This design-build project provided preparatory work for the installation of a new Instrument Landing System (ILS). The ILS consists of an antenna system with primary components at two sites (i.e., Glideslope and Localizer) located at opposite ends of the runway. Work at the two sites consisted of removing and disposing of existing antenna equipment and equipment pads; site preparation for new equipment pads; installing underground conduits for power and communications cabling; installing grounding systems; constructing new equipment pads; and paving new access roads. 1,700 LF of underground fiber was installed. 500 LF of power ductbank and three transformers were installed. Airfield markings, signage and installation of new survey monuments for ILS calibrations were also part of the scope this contract.
$1,682,058
Repair HVAC Periscope Shop
Completion Date
6/19/2016
HVAC system upgrade to meet clean room standards. Scope included selective demolition of existing system; installation of new hot/chilled water generating equipment; air distribution ductwork; control systems; equipment support; electrical power and lighting; installation of a new splined panel ceiling and wall repairs; fire protection system revisions; and commissioning.
$6,857,079
B2050 Medical/Dental Clinic Renovation
Completion Date
4/25/2012
31,750 SF renovation and 3,500 SF addition to a fully operational Medical/Dental clinic. Scope included total HVAC system replacement, repartitioning, interior finishes, and electrical improvements. Concrete and steel addition provided space for administrative offices and medical exam rooms. Extensive phasing and provision of temporary facilities to accommodate ongoing clinic operations.
$11,700,000
Repair CIF Ventilation System, B983, PSNS
Completion Date
9/17/2021
Controlled Industrial Facility (CIF) Building 983 demolition of existing structures on the roof including asbestos and hazardous metals remediation. Installation of a new HVAC system including Stainless Steel ductwork and new air handling units, chillers and exhaust fans. A new raised metal structure platform with a protected roof was installed to house all of the HVAC components with the exception of the chillers.
$1,038,360
B460 Repair Large Slab Rolling Doors
Completion Date
09/08/2020
This project restored operation of four 60-foot tall large slab rolling doors at the west end of Building 460 in the Controlled Industrial Area (CIA) of the Puget Sound Naval Shipyard. Restoring operation to the doors involved retrofitting/restoring the gearboxes; replacing motors, control equipment, and electrical wiring; and providing new enclosures and appurtenances. Audible and visual signaling systems, limit switches and interlocks were installed to facilitate the safe operation of the doors. Deteriorating door panels were restored and painted inside and out. Broken glass panes were replaced. Replacement of aesthetic features adhered to historical restoration requirements.
$7,181,526
Replace HVAC System NHB
Completion Date
10/3/2016
Code-required modification and replacement of 8 air handling units (AHUs), 15 fans, 8 variable air volume (VAV) boxes, and 16 pumps on HVAC systems serving patient care areas and the emergency department. Extensive phasing, infection control, and outage coordination was required to maintain hospital operations.
$384,227
Replace Steamlines
Completion Date
10/11/2011
Phase II of a campus-wide conversion from centralized steam to building-specific, natural gas powered heat exchangers for hot water and heat generation. This phase involved decommissioning portions of the legacy high-pressure steam system and installating new, gas powered equipment for B6 and B61 and integration into the campus energy management control system.
$10,987,000
Dry Dock 4 - Repair Main Dewatering Pumps and Valves
Completion Date
5/21/2021
Overhaul three main dewatering pumps and motors, as well as replacing check and discharge valves, and motor controllers which service Dry Dock 4. Repair/overhaul and restore pumps and motor, included tear down of each system, installing new bearings, impeller and rewind of the motors to achieve sustainable operating conditions allowing continued support of docking activities.
$3,132,900
Replace Boilers 1 & 2 at Steam Plant
Completion Date
03/11/2020
Design-Build Replace Boilers 1 and 2 at the Steam Plant, B384 included the design of a new steam system, demolition and removal of two of three 45,000 pounds per hour (pph) (1300 boiler horse power (BHP)) water tube boilers in the central heating plant and installation of two new 20,700 pph (600 BHP) fire tube boilers. Steam service was maintained by the third existing boiler while replacement work was completed. Boiler replacement scope involved structural upgrade of the existing raised concrete floor slab, reconnection of all services, including feedwater, vent piping, fuel piping, and instrumentation.
$2,671,763
Repair Boiler Feedwater System
Completion Date
7/5/2016
Phased replacement of three existing boiler feedwater pumps with 4-stage, horizontal, specialty pumps; provision of one spare pump; installation of 300 LF of new, seismically-restrained and insulated 8"Ø ductile iron pipe main and reconfigured header pipe main manifold; variable frequency drives and controls; and flow meters.
$596,966
Bldg 13 Energy Upgrades
Completion Date
5/24/2011
Replaced a legacy chiller unit with a new 200-ton, oil-free frictionless magnetic bearing air-cooled centrifugal water chiller. Coordinated replacement to support the ongoing operations of the research faclities served by the chiller. Scope included piping reconfiguration, integration into the existing DDC system and sequence of operations, and miscellaneous interior improvements to support the work.